RESTORATION PHOTO GALLERY
ENTRANCE TO CAMP TOCCOA
Before Images

CIRCA 1942- 1945

Entrance to Camp Toccoa before restoration

Above: Entrance to Camp Toccoa after restoration
Right: Drone view of the regimental monuments across the street from the Camp Toccoa entrance.>>>>>>>>>>>>>
Restoration Images

REGIMENTAL HEADQUARTERS RESTORATIONS
Before Images

CIRCA 1942- 1945



Restoration Images
windows, bathrooms, painting and HVAC
PAVILION
A pavilion was constructed from the ground up to serve as a meeting and gathering place.
Pavilion before Images
Preparing the site for construction



Pavilion Construction Images
grading, slab, building, roof

BARRACKS RECONSTRUCTION
Barrack 1 (506th) completed and the foundations for additional barracks.
Barrack 4 (517th) reconstruction
Progress continues....
Restoration of Barrack 1 (506th) making it ready for year around use by Roesch Construction.
- Interior walls, painting , window trim and rear entry handicap ramp completed
- HVAC system installed by C & A Service, Inc. Gas lines installed by the City of Toccoa
- Electrical completed by Hank Hayes Electrical Contractor
- Dirt was excavated around the barracks compliments of the Phillips Group
Restoration of Barrack 4 (517th) by Carlton Lowry and William Tucker
- Original windows, including glass from original buildings are glazed and painted. Three have been installed with the remainder ready installed in early Dec. 2020
- Soffit boards installed
- Future storage rooms
- Gutters have been added
Gift Shop in the making now open for business

Visit the
'Barracks Store"
Gift Shop